News & Construction Updates

Cosgrove - Stages 501,503 & 505

August 2026: We’re extremely excited to announce the commencement of construction across part of Precinct 5 at Cosgrove by Mendi, marking another exciting milestone in the ongoing growth of our community. Construction is now officially underway across Stages 501, 503 and 505, with bulk earthworks currently in progress. This is an important first step in preparing the land for the next phase of development and, ultimately, creating new homesites for future Cosgrove residents. These stages will gain direct access from the currently under construction Bayswater Road extension 1.

Together, these three stages will deliver 92 additional residential lots to the Cosgrove community. With a diverse range of lot sizes spanning from 352m² through to 896m², the new stages will provide a variety of opportunities for future homeowners, with options to suit different home designs, lifestyles and household needs. As earthworks progress, the site will continue to take shape, transforming the existing landscape into new streets, lots and infrastructure that will form an exciting extension of the Cosgrove community.

Construction across Stages 501, 503 and 505 is currently anticipated to be finalised by mid-2027. We look forward to sharing further updates as construction progresses and these new stages begin to take shape. It’s an exciting time for Cosgrove, and we can’t wait to see this next chapter of the community come to life.

Greater Ascot - Town Centre Stage 1

August 2026: Stage 1 is continuing to progress well, with the civil works now nearing completion. The final quality assurance (QA) documentation has majority been submitted to Council, with only some minor documents left to be submitted to Council as part of the close-out process. With the major roadway and pathway works now substantially complete, the focus is beginning to shift towards the finishing touches that will help bring the Town Centre to life (exciting!). Landscapers will shortly be onsite to commence the landscaping works and will provide the final visual elements to the completed civil infrastructure and begin to establish the look and feel of the Town Centre.

Subject to the completion of the remaining approval and registration requirements, Stage 1 is anticipated to reach on-maintenance and registration in late September. This will represent a significant milestone for the project and will allow the commercial development component to commence, paving the way for the next phase of construction and activity within the Town Centre.

July 2026: July was an exciting and highly productive month for our Stage 1 Town Centre, with significant progress made across multiple areas of the Town Centre. A major milestone was the completion of asphalt surfacing throughout the internal road network, giving a much more defined and finished appearance. Alongside this, kerbing and pedestrian pathways were installed, helping to shape the streetscape and accessibility throughout the Town Centre. Our electrical contractor also made excellent progress, installing essential electrical infrastructure and services that will support our future commercial tenants.

Looking ahead, we expect Quality Assurance (QA) documentation to commence shortly. This is a key milestone in the civil construction process and brings us another step closer to registration. With registration now on the horizon, we are approaching an exciting new phase of the project. Once registration is complete, individual commercial lot owners will be able to commence construction of their buildings, bringing the vision for the Stage 1 Town Centre to life.

June 2026; Civil works continue to progress well on track for Stage 1 of our Town Centre, with road kerb laid and asphalt next to commence. Electrical infrastructure will soon be installed also, meaning we are just months away before each commercial build can commence.

May 2026; Road cut outs are bringing shape to the Stage 1 of our Greater Ascot Town Centre. The establishment of the roads brings excitement to the soon commencement of the construction of tenants shopfronts.

April 2026; With the finalising of site clearing, sees the commencement of the outline of Stage 1 Town Centre starting to take shape. It is exciting to see roadways excavated as this is the first step towards the construction of the Town Centre.

March 2026; Stage 1 of the Town Centre has commenced, with Townsville Earth Moving (TEM) clearing the site. We are excited to welcome a new buzz to our Greater Ascot Estate. More details on retailers are available on the Greater Ascot page https://www.parksideland.com.au/greater-ascot

Bayswater Road Extension - Stage 1

August 2026: The Bayswater Road extension is seeing significant progress being made on the early civil works required to establish the new road connection. The section of the extension running adjacent to Stage 602 has now been cut out, with all major rock-breaking works finalised. This clears the way for the next phase of construction, with works now able to progress towards the formation and construction of the new Bayswater roadway. Excavation works are also continuing along the Weston Street side of the extension to facilitate the upcoming electrical works. These works are an important part of preparing the corridor for the infrastructure and services that will support the completed road.

Traffic management remains in place while construction activities continue across the extension. While these works are underway, we appreciate the patience of motorists and the local community as the project progresses.

July 2026; Construction of the new Bayswater Road extension is now well underway, with Mendi making strong progress on this important piece of infrastructure for our Cosgrove master estate. Bulk earthworks have continued throughout July, with only one final tidy-up blast remaining before this phase of works is complete, marking another key milestone in the delivery of the road extension. Preparation is also underway for construction of the new intersection at Bayswater Road and Weston Street. This will be a significant improvement to the local road network, providing safer and more efficient access to the surrounding precincts, including the new Precinct 5. We are aiming to complete these works as quickly as possible so that normal traffic movements can resume.

During construction, temporary traffic lights have been installed at either end of the work zone to safely manage traffic. These traffic management measures are expected to remain in place for the next few months while the intersection and associated roadworks are completed. We appreciate the community's patience and understanding during these essential infrastructure works and look forward to providing further updates as the project progresses.

May & June 2026; Parkside is excited to see approval of the Stage 1 extension of Bayswater Road. With the extension running adjacent to the south of Precinct 6 and new round-a-bout for future precincts 5, 7, 8 & 10 connection, will see a new extension of vital infrastructure through Townsville. Mendi are the awarded contractor with works to commence in the coming months.

Any questions relative to the construction, including traffic management, please contact Mendi.

Any questions relative to the Mount Louisa walking track, please contact Council

Cosgrove - Weston Street Intersection Upgrade

August 2026: The Weston Street upgrade is progressing well, with our civil contractor continuing works onsite and traffic management measures remaining in place to safely support construction activities. The current focus is on completing the north and south road upgrade connections to the Weston Street intersection, which are important components of the overall upgrade and will continue to improve access and connectivity through the area.

Works are also progressing along Woolcock Street, where the pedestrian pathway is currently being poured. This will provide a new and improved pedestrian connection once complete, further enhancing accessibility and connectivity throughout the precinct. With multiple elements of the upgrade progressing at the same time, the project continues to move forward steadily, with the completed works beginning to take shape.

July 2026: There has been plenty happening on site in July, as the Weston Street/Woolcock Street Intersection Upgrade continues to take shape. Throughout July, RMS has been making steady progress across the project, with earthworks progressing along Weston Street North, as well as earthworks and pavement works supporting the Woolcock Street widening. Footpath works are also continuing along Weston Street South, helping build improved connections for pedestrians and the wider community.

Some works, including earthworks on Weston Street South and drainage works, are currently paused while we work through site requirements, including the existing watermain. Every stage brings us one step closer to delivering the upgraded intersection and improved connectivity for the community.

June 2026: RMS have well since commenced on the Weston Street Intersection upgrade , with traffic management inplace.

April & May 2026: The necessary permits have been obtained and prestart meeting occured. RMS (Contractor), will be commencing late May 2026.

March 2026; Very exciting to see RMS (contractor) set up their site along Woolcock Street to commence the Weston Street Intersection Upgrade. Intersection upgrade works are yet to commence, however in the coming weeks will confirm timings for construction start and finish.

Feb 2026; Following the finalisation of the contract will see commencement of the intersection upgrade commence this month. Once the finalised program is released, further information will be provided here.

Jan 2026; Construction of the signalised intersection upgrade at Weston Street and Woolcock Street will commence shortly, enhancing traffic access to Cosgrove. Delivered concurrently with Stages 601 and 602, works are scheduled to begin in January 2026 and will support improved connectivity and accessibility to the emerging Cosgrove precinct. As Cosgrove emerges, the extension of Bayswater Road through to Cosgrove Drive will come to fruition in coming years.

For more information on the project, click here for details.

Cosgrove - Stages 601 & 602

August 2026: Stage 601 is now very close to completion of the civil works, marking another significant milestone for the Precinct. The final QA documentation is currently being collated and will shortly be submitted to Council as part of the finalisation process. A number of key finishing works have also been completed, with street signage now installed and asphalt finalised across Stage 601. You may also notice the acoustic wall has received a fresh coat of paint, giving the area a more finished appearance as we move towards completion. The retaining walls are also nearing completion, with landscapers expected to be onsite shortly to commence the landscaping works. This will include new landscaping and entry features that will help create a welcoming arrival into the Precinct and add the final touches to Stage 601. With these final works now underway, Stage 601 is rapidly approaching the completion of its civil construction phase.

Stage 602 is also progressing steadily and is not far behind Stage 601. The roads have now been boxed out and the bulk earthworks have been finalised, establishing the foundations for the next phase of civil construction. The next major activities will see retaining wall construction and electrical works commence, continuing the transformation of Stage 602 and bringing the Precinct another step closer to completion. It is exciting to see both stages progressing side by side, with Stage 601 nearing the finish line while Stage 602 continues to build momentum. The dedicated Park in this Precinct will commence not long afterwards.

July 2026; Construction continues to progress across both Stage 601 and Stage 602 at Cosgrove, with several key milestones underway. In Stage 601, acoustic fencing and retaining wall installation is now approximately halfway complete, while pedestrian pathways are being laid throughout the stage. These works are helping to shape the streetscape and bring the development closer to completion. In Stage 602, the roadways have been cut out, clearly defining the layout of the new stage (very exciting!).

Water main and sewer infrastructure installation is also underway in Stage 602, marking another important step in the civil construction process. Looking ahead, landscaping is expected to commence over the coming months, adding the finishing touches to the streetscape and further bringing the development to life. With works progressing across both stages, the development continues to take shape as we move towards the next phase of construction.

June 2026: Retaining wall installation has commenced and soon the installation of the sound wall that abuts Woolcock Street will soon see its installation. Civil works are still well underway with the precinct taking shape nicely. Stage 601 is due to register September 2026 and Stage 602 March 2027. Stay tuned as the finer details of the Stages come to fruition.

May 2026; Stage 601 has seen the continuation of service establishment and road clearing. This is exciting for our Stage 601 buyers. Practical completion for Stage 601 is still on track for mid 2026 and Stage 602 for late 2026.

April 2026; Service pipes are being laid this Month for Stage 601. Road clearings are starting to shape the Precinct. With 75% of the Precinct already released to the public, it is exciting to see a new area of Cosgrove come to life.

March 2026; Construction for Stage 601 is starting to take shape with infrastructure piping being laid and roads continuing to take shape in the precinct. Considering the precinct size and that over 150 lots are being delivered, bulk earthworks are still ongoing. Nethertheless, Mendi are optimistic for a late 2026 finish date, which will see registration for 601 for late 2026 and Stage 602 early 2027. Drone photos courtesy of Mendi.

Feb 2026; Following the establishment of sediment control measures, site clearing is now well underway with clear vision of the new precinct along Weston Street & Woolcock Street. With these sediment protections in place, work has been able to proceed efficiently. Bulk earthworks have advanced steadily, with both clearing and rock crushing proving highly successful. The crushing operations in particular have delivered excellent results. This is great news for Parkside, Precinct 6 buyers and the overall timeline and a positive milestone for the project.

Excitingly, some initial road corridors for parts of Stage 601 have now been cleared. This marks an important step forward and sets the foundation for upcoming civil works within the stage. Despite the challenges that typically come with the wet season, our civil contractor, Mendi, continues to make solid progress on site.

Jan 2026; The latest precinct, 'Sunset Village ' , is located on the eastern side of Cosgrove, offering lots ranging from 300m² to 915m² and a new park in walking distance. Civil works have commenced with initial site clearing underway by Mendi. It is anticipated to finish mid / late 2026 for Stage 601. Registration for the 78 new lots is due in October 2026. Stage 602 will follow with registration for 73 lots due January 2027.

The precinct will have convenience of connectivity, with a substantial intersection upgrade of Weston Street / Woolcock Street and new connectivity to the existing Bayswater Road network. We are excited to see the next precinct in Cosgrove take shape in the coming months.

Greater Ascot Stages 809 & 810

June 2026: Registration has been achieved for Stages 809 & 810 at Greater Ascot. Very exciting news to see 2 new stages officially added to our Greater Ascot community. All builders and Owners have been notified that the commencement of homes can now proceed. It is worthwhile noting that we only have one stage left in Swinley Forest to release - Stage 811. Please contact our Sales Team should you wish for further information.

May 2026; Practical Completion for civil works is basically completed with the QA documents now being finalised for submission into Council. We do expect to see a July registration for Stages 809 & 810. Landscaping Contractor (LIS) will be on site in the coming weeks to install street trees and the meandering bike pathway that wraps around Stages 809 & 810 with the Bohle River. Electrical light poles are onsite, with electricals to be finalised in the coming months.

April 2026; Asphalt being laid and QA documents now being drafted and reviewed sees the registration of Stages 809 & 810 progressing well on track for mid this year. Once QA documents are finalised, will see submission into Council for local approval.

March 2026; Stages 809 and 810 are well advanced now, with stormwater drainage being laid and roading asphalt soon to be finalised. We anticipate Stages 809 and 810 civil work to be completed by May 2026, with registration well on track for July 2026.

Feb 2026; Roadway construction is progressing well, with gravel now laid across internal roads. A significant milestone that brings the community layout to life. Stormwater drainage infrastructure is also well underway. This essential groundwork plays a critical role in ensuring functionality and sustainability for the community, and it’s fantastic to see the civil works advancing steadily.

As expected for this time of year, the wet season has presented some challenges and has impacted certain aspects of the civil works program. Our team is actively managing these conditions and working closely with contractors to maintain momentum wherever possible. At this stage, registration remains on track for August 2026. Should there be any changes to anticipated timeframes, we will communicate these promptly and transparently.

It’s an exciting time, and we look forward to sharing further milestones with you next month.

Jan 2026; With only minimal rain so far this wet season, TEM have progressed with finalising bulk earthworks for the stages and are currently laying down pipework and the initiating of roadways. Registration is still on track for August 2026. Be mindful that site access is still closed to the public until practical completion.

Dec 2025; The high demand Swinley Forest Precinct will grow by 47 new homes by the end of 2026 with construction well underway for Stages 809 & 810 by Townsville Earthmoving (TEM). Earthworks for the Stages are underway with civil works due to finish mid 2026 and registration aiming for around August 2026.

Set away from the hustle and bustle, Swinley Forest is bordered by natural forestland and the Bohle River, providing a quiet, well connected setting. All lots are within walking distance of the Adventure Park and will enjoy direct access to an extensive hike and bike network. Stages 809 & 810 are the 2nd and 3rd final stages of Swinley Forest.

Greater Ascot Stages 501 & 502

April 2026; We have officially received Registration from QLD Titles Office for Stages 501 & 502. To proceed with Settlement, please ensure buyers have unconditional finance obtained. We are very excited to welcome 64 new homes to Greater Ascot. Please ensure Builders send through floor plans to the Covenants Team for review and approval.

March 2026; We anticipate receiving Council documentation late this Month for lodgement with QLD Titles Office early April 2026. All Buyers and Builders will be emailed once all paperwork has been lodged with Titles Office. It can take between 7 - 21 days for Titles to review and register.

Feb 2026; Earthworks are in the final stage with our civil contractor TEM, who are finalising all QA documentation for submission with TCC. We do hope to see a successful site inspection with Council with registration still on track for late March, despite the wet season. Street lights to be installed in the coming months by the electrical contractor and landscaping in the next month will finalise these 2 stages before 64 new homes come to Greater Ascot. We are very excited to welcome the next stage of residents to Greater Ascot.

Jan 2026; Earthworks are progressing very well and it is exciting to see that each Lot has been pegged. We will see the street electricals and landscaping works to be completed in the coming months, following the finalisation of civil works. It is exciting to see fresh roadways take place in these stages. Registration is still on track for March 2026.

Dec 2025; The introduction of our newest precinct Westcroft Park, will welcome more than 300 new homes to the northern parcel of Greater Ascot. This exciting new precinct will offer a diverse range of lot sizes, from 300m² to 1,520m² , catering to a variety of lifestyles.

Stages 501 & 502 are the first collective project to see 64 new homes added to Greater Ascot. Construction commenced in August 2025 and are now well underway by Townsville Earthmoving (TEM). With the roadways almost completely laid and lots being pegged at the moment, civil works are due to finish early 2026 (pending wet season), and registration to follow early/mid 2026.

Westcroft Park will also feature a new park and dedicated hike and bike pathway, seamlessly connecting to the existing network that wraps around the estate enhancing outdoor living for residents. These stages are now sold out. Join the list and register your interest for Stage 503.